Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 4 C A 5 D B 4 E
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E Cmedia:cmpng D
F D
G F
H Emedia:cmpng G
What is the critical path?
multiple choice
ABEH
ABDEH
ACEFGH
ABDFGH
How many weeks will it take to complete the project?
Step by Step Solution