Question: Table A Activity Predecessor Time(weeks) A -- 8 B A 6 C -- 4 D C 9 E A 11 F B 3 G D,

Table A Activity Predecessor Time(weeks) A -- 8 B

Table A Activity Predecessor Time(weeks) A -- 8 B

Table A Activity Predecessor Time(weeks) A -- 8 B A 6 C -- 4 D C 9 E A 11 F B 3 G D, E, F 1 Using Table A, what is the earliest completion time for this project? Multiple Choice O O 18 weeks 19 weeks 20 weeks 21 weeks B 2 OX F E 3 For the network shown in Fig. 7.1, which of the following is the critical path? Multiple Choice . ACDEF ACEF ACDF ABDF D