Question: Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor: BCWS BCWP ACWP BAC EAC 7 6 6
Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor:
BCWS BCWP ACWP BAC EAC
7 6 6 10 10
Pick the true statement from the answers below:
a.Based on the Percent Spent and the Percent Complete, the contractor is on track to complete the work within budget.
b.Based on the Percent Spent and the Percent Complete, the contractor will run out of money before the work is completed.
c.Based on the Percent Scheduled and Percent Spent, the contractor will complete the work on time.
d.Based on the Percent Scheduled and Percent Complete, the contractor will complete the work on time.