Question: Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor: BCWS BCWP ACWP BAC EAC 7 6 6

Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor: BCWS BCWP ACWP BAC EAC 7 6 6 10 10 Based on the IPMR data on this component, what should we tell the Program Manager? Answers: a. The contractor is right on budget, but there are tasks that are currently behind schedule. b. The contractor will complete this project well ahead of schedule. c. The contractor will complete this project under budget. d. The contractor will complete this project ahead of schedule and will only be 5% over budget