Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 26 0.1

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 26 0.1 B E 25 1 C D 18 0.2 D End 18 3.7 E End 15 0 What is the probability that the project will be completed within 70 days? a. 0.25 b. 0.82 c. 0 d. 1 e. 0.18