Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 74 0.13

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 74 0.13
B E 56 0.25
C D 13 0.31
D End 35 0.56
E End 13 0.75

What is the probability that the project will be completed within 126 days?

a.

0.18

b.

0.25

c.

0.82

d.

1

e.

0