Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 74 0.13
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 74 | 0.13 |
| B | E | 56 | 0.25 |
| C | D | 13 | 0.31 |
| D | End | 35 | 0.56 |
| E | End | 13 | 0.75 |
What is the probability that the project will be completed within 126 days?
a.
0.18
b.
0.25
c.
0.82
d.
1
e.
0