Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 39 0.2
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 39 | 0.2 |
| B | E | 17 | 0.25 |
| C | D | 24 | 0.26 |
| D | End | 38 | 0.54 |
| E | End | 27 | 0.75 |
What is the probability that the project will be completed within 105 days?
a.
1
b.
0.18
c.
0.25
d.
0
e.
0.82
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts