Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 39 0.2

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 39 0.2
B E 17 0.25
C D 24 0.26
D End 38 0.54
E End 27 0.75

What is the probability that the project will be completed within 105 days?

a.

1

b.

0.18

c.

0.25

d.

0

e.

0.82