Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 96 0.1

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 96 0.1
B E 23 1
C D 31 0.37
D End 36 3.53
E End 27 0

What is the probability that the project will be completed within 171 days?

a.

1

b.

0.25

c.

0

d.

0.18

e.

0.82