Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 96 0.1
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 96 | 0.1 |
| B | E | 23 | 1 |
| C | D | 31 | 0.37 |
| D | End | 36 | 3.53 |
| E | End | 27 | 0 |
What is the probability that the project will be completed within 171 days?
a.
1
b.
0.25
c.
0
d.
0.18
e.
0.82