Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 118 0.16
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 118 | 0.16 |
| B | E | 42 | 0.25 |
| C | D | 43 | 0.11 |
| D | End | 44 | 0.73 |
| E | End | 12 | 0.75 |
What is the probability that the project will be completed within 209 days?
a.0.25
b.0.82
c.0
d.1
e.0.18