Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 118 0.16

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 118 0.16
B E 42 0.25
C D 43 0.11
D End 44 0.73
E End 12 0.75

What is the probability that the project will be completed within 209 days?

a.0.25

b.0.82

c.0

d.1

e.0.18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!