Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 10 0.27
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 10 | 0.27 |
| B | E | 10 | 0.25 |
| C | D | 13 | 0.27 |
| D | End | 25 | 0.46 |
| E | End | 23 | 0.75 |
What is the probability that the project will be completed within 52 days?
0.18
b.
0
c.
0.25
d.
1
e.
0.82