Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 10 0.27

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 10 0.27
B E 10 0.25
C D 13 0.27
D End 25 0.46
E End 23 0.75

What is the probability that the project will be completed within 52 days?

0.18

b.

0

c.

0.25

d.

1

e.

0.82