Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A,B A 55 0.14 B E 44 1

A project has five activities with the durations
A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A,B A 55 0.14 B E 44 1 D 11 0.32 D End 17 3.54 E End 14 0 What is the probability that the project will be completed within 91 days? a. 0 b. 0.18 c. 0.82 d. 0.25 e. 1