Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 40 0.31

A project has five activities with the durations (days) listed below:
Activity Precedes Expected Duration Variance
Start A, B - -
A C 40 0.31
B E 32 0.25
C D 21 0.35
D End 26 0.34
E End 13 0.75
What is the probability that the project will be completed within 141 days?