Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 40 0.31
| A project has five activities with the durations (days) listed below: | ||||||
| Activity | Precedes | Expected Duration | Variance | |||
| Start | A, B | - | - | |||
| A | C | 40 | 0.31 | |||
| B | E | 32 | 0.25 | |||
| C | D | 21 | 0.35 | |||
| D | End | 26 | 0.34 | |||
| E | End | 13 | 0.75 | |||
| What is the probability that the project will be completed within 141 days? | ||||||