Question: Urgent A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B C 87 0.23 B E

Urgent

Urgent A project has five activities with the

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B C 87 0.23 B E 86 0.25 IC D 47 0.28 End 24 0.49 E End 16 0.75 What is the probability that the project will be completed within 162 days? a. 1 O b. 0.25 C. 0.18 d. 0.82 e. 0