Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A 36 0.37 E 14 0.25

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A 36 0.37 E 14 0.25 D 34 0.34 End 37 0.29 E End 36 0.75 What is the probability that the project will be completed within 111 days? a. 0.18 O b. 0 C. 1 d. 0.82 e. 0.25