Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A 13 0.24 B E 10

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A 13 0.24 B E 10 0.25 C D 40 0.34 D End 26 0.42 E End 15 0.75 What is the probability that the project will be completed within 83 days? a. 1 O b. 0.25 o c. 0.18 O d. 0 e e. 0.82