Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 95 0.35 B E

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B A C 95 0.35 B E 69 0.25 C D 21 0.31 D End 40 0.34 E End 23 0.75 What is the probability that the project will be completed within 160 days? a. 0.82 b. 0.25 O c. 0 O d. 0.18 O e. 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!