Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 108 0.16

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 108 0.16
B E 22 1
C D 18 0.1
D End 21 3.74
E End 16 0

What is the probability that the project will be completed within 155 days?

a. 0.82

b. 0.25

c. 0.18

d. 1

e. 0

Step by Step Solution