Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 108 0.16
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 108 | 0.16 |
| B | E | 22 | 1 |
| C | D | 18 | 0.1 |
| D | End | 21 | 3.74 |
| E | End | 16 | 0 |
What is the probability that the project will be completed within 155 days?
a. 0.82
b. 0.25
c. 0.18
d. 1
e. 0