Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 121 0.26

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 121 0.26
B E 56 0.25
C D 15 0.23
D End 49 0.51
E End 38 0.75

What is the probability that the project will be completed within 189 days?

a.

0.18

b.

1

c.

0.82

d.

0.25

e.

0