Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 113 0.14
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 113 | 0.14 |
| B | E | 73 | 0.25 |
| C | D | 47 | 0.22 |
| D | End | 33 | 0.64 |
| E | End | 21 | 0.75 |
What is the probability that the project will be completed within 197 days?
a.
1
b.
0.25
c.
0.82
d.
0
e.
0.18
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts