Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 113 0.14

A project has five activities with the durations (days) listed below:

Activity Precedes Expected Duration Variance
Start A, B - -
A C 113 0.14
B E 73 0.25
C D 47 0.22
D End 33 0.64
E End 21 0.75

What is the probability that the project will be completed within 197 days?

a.

1

b.

0.25

c.

0.82

d.

0

e.

0.18