Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B C 101 0.13 IB E 73

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B C 101 0.13 IB E 73 1 C D 38 10.15 ID End 26 3.72 IE End 25 10 What is the probability that the project will be completed within 173 days? O a. 0 O b. 0.25 C. 0.18 d. 1 e. 0.82