Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Duration Variance Start A, B - - A C 98 0.16
A project has five activities with the durations (days) listed below:
| Activity | Precedes | Expected Duration | Variance |
| Start | A, B | - | - |
| A | C | 98 | 0.16 |
| B | E | 15 | 1 |
| C | D | 21 | 0.3 |
| D | End | 42 | 3.54 |
| E | End | 22 | 0 |
What is the probability that the project will be completed within 169 days?
a.
0.18
b.
0.25
c.
0
d.
1
e.
0.82