Question: Activity Start A B C D E F G H End Time 0 1.58 2.68 2.56 1.89 3.21 3.83 2.30 3.00 0 a) The Project
| Activity | Start | A | B | C | D | E | F | G | H | End |
| Time | 0 | 1.58 | 2.68 | 2.56 | 1.89 | 3.21 | 3.83 | 2.30 | 3.00 | 0 |
a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = (in 2 decimal places) d) The critical activities are = (ex. type in critical activities as ABCD, no comma, no space)