Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 6
D B 1
E C D 4
F D 3
G F 1
H E G 2

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?