Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 6 D B 1 E C D
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 4 |
| C | A | 6 |
| D | B | 1 |
| E | C D | 4 |
| F | D | 3 |
| G | F | 1 |
| H | E G | 2 |
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?